Term
| What are the 6 processes involved with Project Integration Management? |
|
Definition
Develop Project Charter Develop Project Management Plan Direct and Manage Project Execution Monitor and Control Project Work Perform Integrated Change Control Close Project or Phase |
|
|
Term
| What are the inputs of developing the project charter? |
|
Definition
| project statement of work, business case, contract, enterprise encironmental factors, organizational process assets |
|
|
Term
| What are the 4 inputs for developing a PM plan (integration area)? |
|
Definition
project charter outputs from planning processes enterprise environmental factors organizational process assets |
|
|
Term
| What are the 4 inputs to directing and managing project execution in the integration area? |
|
Definition
Project Management plan approved change requests enterprise environmental factors organizational process assets |
|
|
Term
| What are the 4 inputs to monitoring and controlling project work (integration)? |
|
Definition
Project Management Plan Performance Reports Enterprise environmental factors organizational process assets |
|
|
Term
| What are the 5 inputs to performing integrated change control (integration)? |
|
Definition
project management plan work performance information change requests enterprise environmental factors organizational process outputs |
|
|
Term
| What are the three inputs for closing a project or phase (integration)? |
|
Definition
project management plan accepted deliverables organizational process assets |
|
|
Term
| What is the output of developing project charter? |
|
Definition
|
|
Term
| What is the output from developing a project management plan? |
|
Definition
|
|
Term
| What are the 5 outputs from directing and managing project execution (integration)? |
|
Definition
| deliverables, work performance information, change requests, project management plan updates, project document updates. |
|
|
Term
| What are the 3 ouputs from monitoring and controlling project work (integration)? |
|
Definition
| Change Requests, Project Management Plan Updates, Project Document Updates |
|
|
Term
| What are the three outputs from performing integrated change control (integration)? |
|
Definition
| change request status updates, project management plan updates, project document updates |
|
|
Term
| What are the two ouputs from closing a project or phase (integration)? |
|
Definition
final product, service, or result transition Organizational process assets updates |
|
|
Term
| What three things are included in a project statement of work? |
|
Definition
| business need, product scope description, strategic plan |
|
|
Term
| What three things might a change request include? |
|
Definition
| Corrective Action, Preventative Action, Defect Repair |
|
|
Term
| What are the 5 processes involved in scope management? |
|
Definition
| Collect Requirements, Define Scope, Create WBS, Verify Scope, Control Scope |
|
|
Term
| What are the two inputs of collecting requirements (scope management)? |
|
Definition
Project Charter Stakeholder Register |
|
|
Term
| What are the 3 inputs of defining scope? |
|
Definition
| project charter, requirements documentation, organizational process assets |
|
|
Term
| What are the 3 inputs for creating a WBS? |
|
Definition
| Project Scope statement, requirements documentation, organizational process assets |
|
|
Term
| What are 4 inputs for verifying scope? |
|
Definition
| project managmenet plan, requirements documentation, requirements traceability matrix, validated deliverables |
|
|
Term
| What are 5 inputs of controlling scope? |
|
Definition
| project amnagement plan, work perfomrance information, requirements documentation, requirements traceability matrix, organizational process assets |
|
|
Term
| What are the 3 ouputs of collecting requirements? |
|
Definition
| requirements documentation, requirements management plan, requirements traceability matrix |
|
|
Term
| What ar e3 ouputs of defining scope? |
|
Definition
| project scope statement, project document updates |
|
|
Term
| What are 4 outputs of creating WBS? |
|
Definition
| WBS, WBS dictionary, scope baseline, project document updates |
|
|
Term
| What are 3 outputs of verifying scope? |
|
Definition
| accepted deliverables, change requests, project document updates |
|
|
Term
| What are 5 outputs of controlling scope? |
|
Definition
| work performance measurements, organizational process assets updates, change requests, project management plan updates, project document updates |
|
|
Term
| What are 8 tools & techniques that can be used for collecting requirements? |
|
Definition
| interviews, focus groups, facilitated workshops, group creativity techniques, group decision making techniques, questionnaires/surveys, observations, prototypes |
|
|
Term
| What is the main tool/technique for controlling scope? |
|
Definition
|
|
Term
| WHat are 4 tools and techniques used to define scope? |
|
Definition
| expert judgement, product analysis, alternatives identification, facilitated workshops |
|
|
Term
| What is the main technique for creating WBS? |
|
Definition
|
|
Term
| What is the main technique for verifying scope? |
|
Definition
|
|
Term
| What are 4 ways of reaching a group decision when gathering requirements? |
|
Definition
| unanimity, majority, plurality, dictatorship |
|
|
Term
| What are three components of the scope baseline? |
|
Definition
| project scope statement, wbs, wbs dictionary |
|
|